Category Archives: Stream Restoration

Penfield Pond Dam Removal FS Completed for Essex County and the Town of Crown Point (NY)

In September 2025, Natural Systems Engineering and its partners River Research and Restoration, LLC and the Onondaga Environmental Institute (OEI) completed a feasibility study for the removal of the Penfield Pond Dam, a historic dam constructed in the late 1800s to provide power for the former iron works located in Ironville, New York. 

The FS was undertaken by the Town of Crown Point in response to NYSDEC inspections identifying the dam as a Grade B intermediate hazard indicating that a dam failure may result in damage to infrastructure or is likely to pose the threat of personal injury or substantial economic loss or substantial environmental damage. 

The scope of the FS consisted of: 1) a Field Investigation (including preparation of a supporting Quality Assurance Project Plan) to characterize certain biological, physical and chemical characteristics of the Penfield Pond and Putnam Creek; 2) an Environmental Review to identify environmental, conservation, historic, or archaeological features that might impact a dam removal project, and 3) a feasibility assessment of a potential dam removal project with respect to criteria identified by NYSDEC (infrastructure, historic resources, and sediment management), as well as biota and cost.

Based on the scope-of-work performed, the FS indicated that significant impacts to infrastructure, historic resources or biota as a result of either a complete or partial dam removal are not anticipated. In-stream management of sediments, that is allowing impounded sediments to naturally erode and be transported downstream following either a complete or partial dam removal, appears to be the most cost-effective
means of sediment management, with few if any deleterious downstream impacts expected.

The FS also concluded that either a complete dam removal (i.e. removal of all imported dam construction materials to the pre-existing streambed elevation) or a partial demolition (i.e. removal of approximately ½ of the dam height) are feasible
removal alternatives, with a partial demolition being lesser in cost (roughly estimated at $106,000-$122,000) than that of a complete dam removal (roughly estimated at $163,000), but also not fully eliminating the risk of a future dam failure as a complete removal would. Allowing dam abutments to remain following either complete or partial removal would preserve some remnants of the historical structure for the historical site and museum associated with the project area.

 

Restoration of Tributary 26 to Butternut Creek (LaFayette, NY) Nearing Completion

On June 30-July 1, 2017 an extreme rainfall event caused the lateral migration of the of Tributary 26 to Butternut Creek located south of Colton Road in LaFayette, New York.  The migration of the stream channel caused undercutting and erosion of the stream bank to the east and deposition of new point breaks downstream.

Tributary 26 looking southerly. Eroded streambank visible on left (east).

In collaboration with Dr. Ted Endreny from SUNY ESF and the Onondaga County Soil and Water Conservation District, NSE developed a design plan for the restoration of this stretch of Tributary 26 and was intended to reclaim riparian area east of the creek for the landowner and implementing conservation and restoration techniques intended to prevent future lateral migration of the creek and preserving it’s natural function.  The design followed Rosgen stream restoration principles and consisted of:

  • reestablishment of the creek channel to the west
  • bendway weirs to deflect and dissipate energy away from the eroding east stream bank
  • rock riffles and large stones to dissipate energy within the newly reestablished stream channel
  • dogwood plantings in the reclaimed floodbank and fascines to protect the edge of bank.

Design plan for Tributary 26 Restoration

Construction was initiated per the design plan by the selected contractor J&J Landscaping the week of November 27, 2017 and earthwork completed on December 8.  Plantings to follow in mid-December.

Reestablished creek looking southerly from Colton Road.

Assuming continuing adaptive management measures to be informed by the landowner, the reestablished creek and energy dissipation measures will provide for a stable planform, yet able to pass extreme events via a connected functioning floodplain.