Residential Geothermal Design and Install Completed in DeWitt, New York!

In late 2025/early 2026, Natural Systems Engineering (NSE) completed a design and installation of a 3-ton water-to-air ground source heat pump (GSHP) system in DeWitt New York.  The heat pump is a Geostar Sycamore system and the ground loop consisted of one 350-ft vertical closed loop with 1.25″ HDPE piping and thermal grout.  

For this project we worked with partners Utter Well Drilling (Lodi, New York) and EMM Heating Services (Croghan, New York) for the ground loop and the heat pump install, respectively.  

The ground loop design report, energy model, and rebate application along with supporting documentation were prepared and submitted by NSE to support the National Grid Clean Heat Program rebate application. This system was one of the first to leverage the latest Clean Heat Program rebates for 2026 of $20,000 (!) for full-load installations.  

Penfield Pond Dam Removal FS Completed for Essex County and the Town of Crown Point (NY)

In September 2025, Natural Systems Engineering and its partners River Research and Restoration, LLC and the Onondaga Environmental Institute (OEI) completed a feasibility study for the removal of the Penfield Pond Dam, a historic dam constructed in the late 1800s to provide power for the former iron works located in Ironville, New York. 

The FS was undertaken by the Town of Crown Point in response to NYSDEC inspections identifying the dam as a Grade B intermediate hazard indicating that a dam failure may result in damage to infrastructure or is likely to pose the threat of personal injury or substantial economic loss or substantial environmental damage. 

The scope of the FS consisted of: 1) a Field Investigation (including preparation of a supporting Quality Assurance Project Plan) to characterize certain biological, physical and chemical characteristics of the Penfield Pond and Putnam Creek; 2) an Environmental Review to identify environmental, conservation, historic, or archaeological features that might impact a dam removal project, and 3) a feasibility assessment of a potential dam removal project with respect to criteria identified by NYSDEC (infrastructure, historic resources, and sediment management), as well as biota and cost.

Based on the scope-of-work performed, the FS indicated that significant impacts to infrastructure, historic resources or biota as a result of either a complete or partial dam removal are not anticipated. In-stream management of sediments, that is allowing impounded sediments to naturally erode and be transported downstream following either a complete or partial dam removal, appears to be the most cost-effective
means of sediment management, with few if any deleterious downstream impacts expected.

The FS also concluded that either a complete dam removal (i.e. removal of all imported dam construction materials to the pre-existing streambed elevation) or a partial demolition (i.e. removal of approximately ½ of the dam height) are feasible
removal alternatives, with a partial demolition being lesser in cost (roughly estimated at $106,000-$122,000) than that of a complete dam removal (roughly estimated at $163,000), but also not fully eliminating the risk of a future dam failure as a complete removal would. Allowing dam abutments to remain following either complete or partial removal would preserve some remnants of the historical structure for the historical site and museum associated with the project area.

 

Colvin Avenue Apartments Geothermal Design Completed!

NSE completed the ground loop design for 2-building apartment complex in Albany, New York for the U.W. Marx Construction Company and Regan Development in November 2024.  The buildings represent a total design load of almost 100 tons and the ground loop consists of eighteen vertical wells drilled to 620 ft.  The design was based on heat loads calculated using Carrier’s Hourly Analysis Program (HAP) and field thermal conductivity testing performed by Earth Energy Connections, Inc. (Hudson, New York).    

Drilling of the geothermal wellfield was completed in late 2024 with construction of the apartments to be completed in 2025. 

Geothermal Install Competed at Schmid Guest House in Willsboro, New York

The installation of a ground source heat pump (geothermal) HVAC system designed by NSE in 2024 was completed in May 2025 with our partners EMM Heating Services (Lowville, NY) and Wood Well Drilling (Star Lake, NY).  The heat pump is a Energy Catalyst hybrid system that provides air conditioning and hot water heat for a hydronic distribution system, served by a 320 ft closed loop geothermal well.  

Lion Factory Apartments Geothermal Project Completed!

The Lion Factory Apartments now occupied!  Natural Systems Engineering designed the vertical ground loop heat exchanger to heat and cool, and provide domestic hot water for this former factory converted to a 150 unit apartment building in Troy, New York in 2024.  The ground loop consists of ninety closed loop wells drilled to 450 ft in depth

At the time this was the largest ground source heat pump system completed under National Grid’s Clean Heat Program.  Very thankful to U.W. Marx and Regan Development for the opportunity to work on this project!  

Homer, NY Geothermal Project Completed!

In late 2020 NSE completed our final geothermal project for the year in Homer, New York.  The design was of a closed loop ground source heat exchanger for a 4-ton water-to-air system to serve a residence on Houghton Hill Road, Homer.  Modeling of design heat loss using the ASHRAE Manual J  program and the design of the ground loop using LoopLink software by NSE allowed the owner to obtain a Clean Heat rebate of $6450 from National Grid.

One of the three trenches for the six horizontal GHEX loops associated with the project
Trench and two-pipe laying configuration of GHEX

NSE is approved by NYSERDA (and affiliated utilities) as a designer and installer of ground source heat pump (GSHP) systems, thus making owners eligible for rebates as per the above.  Contact us for your residential or commercial project!

Restoration of Tributary 26 to Butternut Creek (LaFayette, NY) Nearing Completion

On June 30-July 1, 2017 an extreme rainfall event caused the lateral migration of the of Tributary 26 to Butternut Creek located south of Colton Road in LaFayette, New York.  The migration of the stream channel caused undercutting and erosion of the stream bank to the east and deposition of new point breaks downstream.

Tributary 26 looking southerly. Eroded streambank visible on left (east).

In collaboration with Dr. Ted Endreny from SUNY ESF and the Onondaga County Soil and Water Conservation District, NSE developed a design plan for the restoration of this stretch of Tributary 26 and was intended to reclaim riparian area east of the creek for the landowner and implementing conservation and restoration techniques intended to prevent future lateral migration of the creek and preserving it’s natural function.  The design followed Rosgen stream restoration principles and consisted of:

  • reestablishment of the creek channel to the west
  • bendway weirs to deflect and dissipate energy away from the eroding east stream bank
  • rock riffles and large stones to dissipate energy within the newly reestablished stream channel
  • dogwood plantings in the reclaimed floodbank and fascines to protect the edge of bank.

Design plan for Tributary 26 Restoration

Construction was initiated per the design plan by the selected contractor J&J Landscaping the week of November 27, 2017 and earthwork completed on December 8.  Plantings to follow in mid-December.

Reestablished creek looking southerly from Colton Road.

Assuming continuing adaptive management measures to be informed by the landowner, the reestablished creek and energy dissipation measures will provide for a stable planform, yet able to pass extreme events via a connected functioning floodplain.

NSE’s Urban Geothermal Project Featured on Spectrum News and ESF’s “Going Green” Program!

Natural Systems Engineering’s Kyle Thomas discusses the performance of our recent urban retrofit geothermal project and NYSERDA’s incentives on Spectrum News’s and ESF’s “Going Green” television program.

Front Yard Geothermal Drilling – Tipperary Hill, Syracuse

 

Solar Power during the Eclipse!

Here in Central New York we experienced 68% of totality during the August 21, 2017 solar eclipse.  There seemed to be general agreement among observers that there wasn’t a significant perceptible reduction in ambient light during the event.  But check out the reduction in solar PV output during the ~1:30 to ~3:30 PM timeframe and the peak at 2:38 PM in the plot below.  The reduction in output is significant, but comparable to a cloudy period based on a comparison with the cloudy afternoon of August 15 the previous week.

Solar power on Eclipse Day.

Porous asphalt vehicle display lot completed for Crest Acura!

With funding under Onondaga County’s award-winning Save the Rain program, Crest Acura’s porous asphalt lot was completed this summer.  The project was designed by Natural Systems Engineering and constructed by Lan-Co Construction (East Syracuse, New York).  The porous asphalt was designed to capture runoff from the 10,000 sq ft porous surface and the 9950 sq ft impervious asphalt lot located to the northeast.  Roughly 1000 sq ft of greenspace was added to replace asphalt in the right-of-way of the City of Syracuse.

The project will manage a minimum of 400,000 gal of strormwater per year, removing that flow from Syracuse’s combined sewer system.